Mastering Plasterboard Installation on Steel Frames: An Owner-Builder's Guide
Introduction
Congratulations on embarking on your journey as an owner-builder, especially with the increasingly popular choice of a steel frame kit home! This guide is meticulously crafted to empower you with the knowledge and practical skills required for successfully installing plasterboard on your steel frame. As an owner-builder in Australia, you are taking on a significant responsibility, and achieving a professional finish with your internal linings is crucial for both aesthetic appeal and structural integrity. This guide aims to provide an intermediate-level understanding, meaning we'll delve into detailed technical processes, specific measurements, practical tips often shared by experienced tradespeople, and essential troubleshooting advice.
Steel frame construction, particularly with products like TRUECORE® steel from BlueScope Steel, offers numerous advantages, including durability, termite resistance, and straight walls, which simplifies the plasterboard installation process considerably. However, it also presents unique considerations when compared to traditional timber framing. This guide will specifically address these nuances, ensuring you're well-equipped to tackle this critical stage of your build.
Failing to properly install plasterboard can lead to numerous issues, from unsightly cracks and uneven surfaces to compromised sound insulation and fire resistance. By following the detailed instructions and regulatory advice within this guide, you will not only achieve a high-quality finish but also ensure compliance with Australian building codes and standards. We'll cover everything from site preparation and material selection to cutting, fixing, stopping, and rectifying common issues, all while keeping safety and regulatory compliance at the forefront. Prepare to transform your exposed steel frame into beautifully finished interior spaces.
Understanding the Basics
Before diving into the intricate steps of installation, it's vital to have a solid grasp of the fundamental materials and terminology involved. This will form the bedrock of your understanding and decision-making throughout the process.
What is Plasterboard?
Plasterboard, often referred to as drywall or gyprock (a common brand name in Australia), is a panel made of gypsum plaster pressed between two thick sheets of paper. It is used to make interior walls and ceilings. Its advantages include ease of installation, fire resistance, sound dampening properties, and a smooth surface ready for paint or other finishes.
Types of Plasterboard
Selecting the correct type of plasterboard is critical, as different areas of your home have varying requirements:
- Standard Plasterboard: The most common type, suitable for general living areas, bedrooms, and hallways. Typically comes in 10mm or 13mm thickness.
- Fire-Resistant Plasterboard (Fyrecheck/Fire-Rated): Contains glass fibres and other additives to enhance fire resistance. Essential for garages, wall linings in multi-residential buildings, or in areas where a specific Fire Resistance Level (FRL) is required by the NCC. Refer to NCC 2022, Volume One, Section C, Part C2 for specific FRL requirements based on building class and proximity to boundaries.
- Moisture-Resistant Plasterboard (Wet Area/Water-Resistant): Treated with wax or silicone to repel moisture, making it suitable for bathrooms, laundries, and toilets. Often identifiable by a green or blue paper facing. This is distinct from waterproof sheeting (e.g., render board for showers) and still requires a waterproofing membrane in wet areas according to AS 3740.
- Sound-Reducing Plasterboard (Acoustic/Soundchek): Features a higher density gypsum core, sometimes with laminated layers, to improve sound insulation. Ideal for media rooms, studies, or separating living spaces from bedrooms.
- Impact-Resistant Plasterboard: Contains reinforcing mesh or additives for increased durability in high-traffic areas, such as hallways or commercial applications.
- External Plasterboard (CSR CEMINTEL, James Hardie Exotec): While not strictly plasterboard, these fibre cement products are often used for external soffits or cladding and share similar installation principles. Ensure you specify materials suitable for external exposure if needed.
Steel Frame Terminology
Understanding the components of your steel frame is crucial for accurate plasterboard fixing:
- Studs: Vertical members forming the wall frame. In steel frames, these are typically C-section or box section profiles.
- Tracks (or PFC/CHS): Horizontal members (top and bottom plates) that studs fit into. These are often cold-formed steel sections.
- Noggings (or Blocking/Bridging): Horizontal members placed between studs to provide lateral stability, prevent stud rotation, and offer fixing points for services and plasterboard.
- Truecore® Steel: A brand of steel from BlueScope Steel, widely used in residential framing. Known for its strength-to-weight ratio and precise manufacturing, resulting in straight and true frames, which significantly aids plasterboard installation.
- Service Holes: Pre-punched holes in steel studs and noggings to accommodate electrical cabling and plumbing. Always verify these during frame inspection.
Tools and Materials Overview
Having the right tools and materials ready is paramount for an efficient and high-quality installation.
Essential Tools:
- Plasterboard Lifter: Indispensable for ceiling sheets, reducing strain and improving accuracy.
- Tape Measure: At least 8m, ideally with a magnetic tip.
- Utility Knife / Plasterboard Knife: With plenty of spare blades.
- T-Square: For accurate, straight cuts.
- Jab Saw: For detail cuts and cutting around openings.
- Drywall Rasp/Surform Tool: For trimming edges.
- Cordless Drill/Screw Gun: With adjustable clutch, specifically for drywall screws (countersinking head).
- Drywall Screw Setter Bit: Prevents over-driving screws.
- Chalk Line: For marking straight lines on walls and ceilings for stud centres.
- Laser Level: Highly recommended for establishing consistent lines for ceiling sheets and wall panelling, ensuring plumb and level installation.
- Snips/Tin Snips: For cutting light-gauge steel members if adjustments are needed (unlikely for kit homes, but good to have).
- Stud Finder: Essential for locating studs, especially after insulation is installed. Magnetic stud finders are excellent for steel frames.
- Safety Gear: Safety glasses, gloves, dust mask (P2 minimum), hearing protection. Critical for all stages.
Materials:
- Plasterboard Sheets: Correct type and thickness for each area (e.g., 10mm for walls, 13mm for ceilings are common for owner-builders to reduce sag, or even 10mm if battens are at 450mm centres). Check local building codes and manufacturer recommendations.
- Drywall Screws: Specifically designed for steel frames. These have a finer thread and sharp point (self-drilling/self-tapping). Common sizes are 25mm to 35mm. Ensure they are galvanised for exterior applications or wet areas if specified.
- Jointing Compound (Base Coat & Top Coat): Base coat for strength, top coat for finish.
- Paper Jointing Tape: For flat joints.
- Fiberglass Mesh Tape (Self-Adhesive): For repairs, internal corners (sometimes preferred over paper), or butt joints.
- Metal Corner Bead: For external corners, providing a clean, durable edge.
- Internal Corner Tape/Bead: A paper or plastic product for achieving crisp internal corners.
- Adhesive (optional but recommended): Acrylic stud adhesive for walls, especially if battens are not used on ceilings, to reduce nail pops and provide a stronger fix. This must be compatible with steel frames.
Australian Regulatory Framework
Adhering to Australian building regulations and standards is non-negotiable for owner-builders. Compliance ensures safety, structural integrity, and facilitates future resale.
National Construction Code (NCC)
The NCC (formerly the Building Code of Australia - BCA) is the overarching technical document that sets the minimum standards for the design and construction of buildings in Australia. For internal linings, the primary reference is:
NCC 2022, Volume Two (for Class 1 and 10 buildings, i.e., houses and sheds):
- Performance Requirement P2.2.2 - Structural stability: Addresses stability of the framed construction and linings.
- Performance Requirement P2.4.1 - Health and amenity: Includes provisions for damp and weatherproofing, which directly impacts the selection and installation of plasterboard in wet areas.
- Performance Requirement P2.5.1 - Fire resistance and safety: Dictates where fire-resistant linings are required, such as in garages or external walls close to boundaries.
- Part 3.8.1 - Wet Areas: Specifies requirements for waterproofing in bathrooms, laundries, and toilets. This means even moisture-resistant plasterboard needs an appropriate waterproofing membrane installed over it and correctly terminated to comply with AS 3740.
- Part 3.3.4 - Wall and Ceiling Linings (Deemed-to-Satisfy Provisions): This section outlines acceptable methods for fixing plasterboard, permissible sheet thicknesses, and framing requirements (stud spacing, nogging). It often refers to manufacturer specifications and relevant Australian Standards.
Australian Standards (AS/NZS)
These standards provide detailed specifications and testing methods. Key standards relevant to plasterboard installation include:
- AS/NZS 2588:2018 Gypsum Plasterboard: Specifies material properties, dimensions, tolerance, and performance requirements for plasterboard.
- AS/NZS 4600:2018 Cold-formed steel structures: This is critical for understanding the structural aspects of your steel frame and how linings integrate. It influences stud spacing and bracing requirements, which in turn impact plasterboard choice.
- AS/NZS 3740:2021 Waterproofing of domestic wet areas: Dictates the requirements for waterproofing membranes in bathrooms, laundries, and toilets. Plasterboard is typically installed first, then a licensed waterproofer applies the membrane.
- AS 3623:1993 Domestic metal framing: While older, it still provides context for design and installation of metal framing. Modern kit homes often exceed these basic provisions.
- AS 1684 Series (Residential Timber-Framed Construction): While for timber, it provides principles for bracing and loading that can be adapted conceptually to steel frames, particularly regarding how linings contribute to bracing. However, specific steel frame design guides (e.g., from Truecore or Bluescope) should be followed for steel.
Manufacturer Specifications
Always consult the specific installation guides provided by your plasterboard manufacturer (e.g., CSR Gyprock, Boral Plasterboard) and your steel frame manufacturer (e.g., Truecore steel builders). These guides often provide more detailed, product-specific instructions that comply with the NCC and AS/NZS standards, and may include recommendations for screw types, spacing, and adhesive use validated by their engineering.
State-Specific Variations and Regulatory Bodies
While the NCC provides national consistency, states and territories have their own legislation, building acts, and regulatory bodies that oversee its implementation. Owner-builders must be aware of and comply with these local requirements.
- New South Wales (NSW): Regulated by NSW Fair Trading, specifically the Building Commissioner. Building approvals and inspections are managed by local councils or accredited certifiers.
- Queensland (QLD): Administered by the Queensland Building and Construction Commission (QBCC). Building certifiers issue approvals and conduct mandatory inspections.
- Victoria (VIC): Regulated by the Victorian Building Authority (VBA). Building surveyors manage permits and inspections.
- Western Australia (WA): Oversighted by the Building & Energy division of the Department of Mines, Industry Regulation and Safety. Local government building services issue permits.
- South Australia (SA): Regulated by the Office of the Technical Regulator and local councils. Building certifiers are often involved.
- Tasmania (TAS): Administered by Consumer, Building and Occupational Services (CBOS) within the Department of Justice. Permit authorities issue building permits.
Owner-Builder Obligation: As an owner-builder, you are legally responsible for ensuring that all work, including plasterboard installation, complies with the NCC, relevant AS/NZS standards, manufacturer specifications, and your state/territory's building regulations. This includes arranging all necessary inspections by your building certifier/surveyor at the appropriate stages (e.g., prior to lining where insulation and services are checked, and potentially at pre-completion). Failure to comply can result in fines, difficulties with occupancy permits, and insurance issues.
Step-by-Step Process
This section provides a detailed, sequential guide to plasterboard installation specifically for steel frames. Remember to work systematically and maintain a high standard of accuracy.
Step 1: Site Preparation and Safety
This crucial initial step sets the stage for a smooth and safe installation.
- Clear the Work Area: Remove all debris, excess materials, and obstructions from the rooms where plasterboard will be installed. Ensure good lighting throughout.
- Verify Frame Straightness: Even with Truecore steel's precision, double-check all studs and tracks for plumb and square. Use a long level (1.8m-2.4m) or laser level. Report any significant deviations (e.g., greater than 3mm over 2.4m) to your steel frame supplier or engineer, as this can lead to bowing plaster and cracking.
- Check Services: Ensure all electrical wiring, plumbing, and HVAC rough-ins are complete, tested, and inspected (where required by your certifier). No services should obstruct the plasterboard plane.
- Insulation Installation: Ensure wall and ceiling insulation is correctly installed, snug against the frame, and not bunched or gapped. It must not interfere with the plasterboard's flatness, as required by NCC 2022, Volume Two, P2.6.1 and Part 3.12.1.1 (Performance of insulated elements).
- Safety Briefing & Equipment: Conduct a mental safety briefing. Wear all mandatory Personal Protective Equipment (PPE) including safety glasses, P2 dust mask, gloves, and hearing protection. Ensure your ladder or scaffold is stable and rated for your weight plus tools. Follow WHS (Work Health and Safety) regulations for working at heights (safeworkaustralia.gov.au).
WHS Warning: Cuts from plasterboard edges and screws are common. Dust from cutting and sanding plasterboard can cause respiratory issues. Always use a utility knife with a fresh, sharp blade and avoid forcing cuts. Wear a P2 mask when cutting or sanding.
Step 2: Material Storage and Acclimatisation
Proper material handling prevents damage and ensures optimum performance.
- Store Flat: Plasterboard sheets must be stored flat on a level surface, ideally on timber battens, to prevent warping or bowing. Avoid storing them vertically for extended periods.
- Protect from Moisture: Store sheets in a dry environment, protected from rain, humidity, and ground moisture. Moisture can cause warping, mould, and reduce the plasterboard's structural integrity.
- Acclimatisation: Allow plasterboard sheets to acclimatise in the building for at least 24-48 hours before installation, especially in significant temperature or humidity changes. This helps the gypsum core adjust to ambient conditions, reducing the risk of expansion/contraction after installation.
Step 3: Layout and Planning
Strategic planning minimises waste and improves efficiency.
- Ceiling First: Always plasterboard ceilings before walls. This allows the ceiling sheets to be supported by the wall top plates and provides a clean, continuous surface.
- Minimise Joins: Plan your layout to minimise butt joints (where the untapered ends of two sheets meet). Tapered edges are designed for easier filling. Position sheets so that cut edges are mostly at internal corners or along wall/ceiling junctions where they can be covered by cornices or skirting.
- Sheet Orientation: For ceilings, run sheets perpendicular to ceiling battens or rafters/trusses. For walls, sheets can be installed vertically or horizontally. Vertical installation is common for 2.4m or 2.7m ceiling heights, as it provides full-height sheets with typically only one horizontal line of screws to finish. Horizontal installation (often for ceilings over 2.7m) means fewer vertical joins but requires more careful planning for staggered joints across multiple rows.
- Openings: Plan cuts for windows and doors. Position sheet edges so that joins do not fall directly on door or window frames. Joins should be at least 150mm away from the corners of openings to prevent stress cracks.
- Locate Framing: Mark the centre of all steel studs and ceiling battens/trusses on the floor and ceiling frame (for walls) or perimeter walls (for ceilings) using a chalk line. This will guide your screw placement.
Step 4: Cutting Plasterboard
Accuracy is key for tight joints and a professional finish.
- Measure Accurately: Measure twice, cut once. For walls, measure from floor to the underside of the ceiling sheet or top plate. For ceilings, measure from wall to wall.
- Score and Snap: Place the plasterboard face-up on a flat surface or over a straight edge (e.g., another sheet, a sacrificial timber offcut). Using your T-square and utility knife, score deeply along your cut line. Apply firm, even pressure. Snap the board upwards or downwards along the scored line. Then cut the paper backing on the other side.
- Detail Cuts: For complex shapes or around openings, use a jab saw. For small trims, use a drywall rasp to smooth edges.
- Edge Treatment: For cut edges that will form a butt joint, slightly bevel the edge with a rasp to create a very slight 'V' groove. This provides a small channel for the jointing compound, improving adhesion and reducing the prominence of the butt joint.
Step 5: Fixing Plasterboard to Steel Frames (Ceilings First)
This is where the specific considerations for steel frames become prominent. The fixing should be strong, flat, and consistent.
Ceiling Installation:
- Positioning: Using a plasterboard lifter, raise the first full ceiling sheet into position. Ensure it's tight against the walls and aligned correctly.
- Adhesive (Optional but Recommended): Apply a continuous bead of acrylic stud adhesive along the face of the steel ceiling battens/trusses where the sheet will sit. This creates 'bond-breaking' points with the steel to reduce movement and improve adhesion. Ensure adhesive is compatible with steel framing.
- Screwing: Use self-drilling, self-tapping drywall screws (fine thread, often black or grey phosphate coated) of appropriate length (e.g., 25-35mm). Screw every 150mm-200mm along the perimeter and every 300mm along intermediate battens/trusses. Screws should be recessed slightly below the paper surface without breaking the paper, using a drywall screw setter bit. Do NOT over-tighten!
- Sheet Gaps: Leave a 3-5mm gap around the perimeter of the ceiling sheets adjacent to walls. This allows for structural movement and is covered by cornices.
- Stagger Joints: Stagger end-butt joints on successive rows of sheets to prevent a continuous line of weak points.
Wall Installation:
- Start Point: Typically, start in a corner and work your way around the room. For full-height sheets (e.g., 2.4m or 2.7m), install them vertically.
- Adhesive: Apply a continuous bead of approved acrylic stud adhesive along the face of each steel stud where the sheet will be fixed. This helps prevent drumming and provides supplemental strength.
- Screwing: Screw perimeter edges every 150-200mm and intermediate studs every 300mm. Maintain consistent screw depth using the setter bit. Ensure screws penetrate the steel stud by at least 10mm. For Truecore steel frames, the profile of the stud is typically an open C-section. Ensure your screws are designed for fastening to light gauge steel (<1.2mm thickness) and not heavier hot-rolled steels.
- Cut-outs for Services: Carefully measure and cut out openings for electrical outlets, light switches, and plumbing fixtures before fixing the sheet. Use a jab saw or hole saw. Make the cut-out slightly larger than the box, ensuring the plasterboard doesn't sit on the box, but around it.
- Door and Window Reveals: Accurately cut plasterboard to form the reveals around windows and doors. These often require careful measurement and trimming to ensure a neat fit.
- Horizontal Gaps: If using horizontal sheeting (e.g., two rows of 1.2m sheets for a 2.4m wall), ensure the horizontal joint is supported by a nogging or timber blocking behind it. Stagger vertical joints.
BlueScope Steel/TRUECORE® Specific Note: Steel frames, especially those manufactured from Truecore steel, are engineered for precise dimensions. This means fewer shims or packing strips are generally required compared to timber. However, it also means that any slight imperfections in your frame (unlikely with quality kit homes, but possible) will be more obvious. The fine thread screws designed for steel are critical; coarse thread screws used for timber will not provide adequate grip or pull-out strength in steel.
Step 6: Jointing and Stopping (Finishing)
This is where the walls and ceilings transform from raw sheets into a smooth, paintable surface. Patience and attention to detail are paramount.
- Preparation: Ensure all screw heads are recessed and all cut edges are clean. Lightly sand any proud areas. Wipe down the plasterboard to remove dust.
- Applying Base Coat:
- Joint Tape: Apply jointing compound (base coat) to all tapered joints, butt joints, and internal/external corners. Embed paper jointing tape into the wet compound on tapered and butt joints, pressing it firmly with a wiping knife to remove air bubbles and excess compound. For internal corners, fold the paper tape down the centre, apply compound to both sides of the corner, embed the tape, and wipe flush.
- Screw Heads: Apply a small amount of base coat over each screw head, filling the dimple.
- External Corners (Corner Bead): Cut metal corner bead to length. Apply base coat to both sides of the external corner. Press the corner bead into the wet compound, ensuring it's plumb and true. Use a wiping knife to embed it firmly, ensuring a thin, even coat of compound secures it.
- Second Coat (Base Coat): Once the first coat of base coat is dry (allow 24 hours, or as per manufacturer instructions), apply a wider, feathered second coat over all taped joints and screws. The goal is to build up the joint gradually so it blends seamlessly with the plasterboard surface.
- Applying Top Coat: Once the base coat is fully dry, apply the finishing (top) coat. This is a finer compound, designed for a smooth finish.
- Apply a thin, wide coat over all previously treated joints and screw heads. Feather the edges out to blend with the sheet. Use a wider trowel (e.g., 250mm or 300mm) for this step.
- For external corners, apply top coat to both faces of the metal bead, feathering out. Ensure no metal is visible.
- Sanding: Once the top coat is thoroughly dry (24-48 hours depending on humidity), carefully sand all jointed areas and screw heads. Use a fine-grit sandpaper (e.g., 180-220 grit) on a sanding pole or block. The aim is to create a perfectly smooth, flat surface. Be careful not to sand through the paper facing of the plasterboard.
Professional Tip: For a truly professional finish, some tradespeople will apply a third, very thin, very wide top coat, and then a final fine sanding. Achieving perfectly flat joints requires practice. Over-sanding can expose the paper, leading to future paint absorption issues.
Step 7: Cornice Installation
Cornices cover the gap between wall and ceiling sheets and add a decorative finish.
- Measure and Cut: Measure each wall length. Cut cornices to size, using a mitre box and saw for accurate internal and external corner cuts. Compound mitre saws are excellent for this.
- Adhesive: Apply cornice adhesive (a specific quick-setting plaster-based adhesive) to the back edges of the cornice where it will meet the wall and ceiling. Apply a continuous bead.
- Position and Fix: Press the cornice firmly into place. Ensure a tight fit at the wall/ceiling intersection and at all corners. Wipe away excess adhesive immediately with a wet sponge. Use temporary pins or small nails if needed on the wall or ceiling frame to hold it in place while the adhesive sets, removing them carefully once dry. For steel frames, be cautious with nails – adhesive is primary. Alternatively, some cornice adhesives have sufficient grab without much mechanical fixing, especially for lighter cornices.
Practical Considerations for Kit Homes
Steel frame kit homes offer distinct advantages but also require specific approaches during plasterboard installation.
Advantages of Steel Frames for Plasterboard
- Dimensional Stability: Truecore steel frames are not susceptible to twisting, warping, or shrinking due caused by moisture changes, unlike timber. This leads to extremely straight and true walls and ceilings, making plasterboard installation significantly easier and reducing cracking potential.
- Termite Proof: No need for chemical treatments or concerns about timber degradation impacting linings.
- Pre-Punched Service Holes: Generally, steel frames come with pre-punched holes in studs and noggings, simplifying cable and pipe routing.
Specific Challenges and Solutions
- Screw Selection: As highlighted, using the correct self-drilling, fine-thread drywall screws designed for light gauge steel is non-negotiable. Timber screws will not penetrate or hold adequately.
- Acoustics: Steel frames can sometimes transmit sound more readily than timber due to steel's density. If sound insulation is a priority (e.g., between bedrooms or an attached garage), consider using acoustic plasterboard, sound-dampening insulation (e.g., rockwool), or even a double-layer plasterboard system with staggered joints and a resilient channel system (furring channels) to decouple the plasterboard from the frame. This also contributes to NCC 2022, Volume Two, P2.4.6 for sound transmission class (STC) ratings.
- Thermal Bridging (Minor): While not directly impacting plasterboard installation, steel frames can create minor thermal bridges. Ensure insulation is installed correctly to mitigate this. The plasterboard itself contributes minimally to thermal resistance.
- Cutting Steel: While typically not needed during plasterboard, if any minor frame adjustments are required, use appropriate cutting tools (e.g., snips, grinder with caution and proper PPE for sparks and metal dust) rather than tools meant for timber.
- Adhesive Compatibility: Always verify that any adhesives (stud adhesive, cornice adhesive) are compatible with steel substrates. Most modern acrylic stud adhesives are, but double-checking with the product data sheet is wise.
- Fixing to PFC/CHS Sections: If your frame utilizes heavier PFC (Parallel Flange Channel) or CHS (Circular Hollow Section) members for specific structural elements (e.g., large openings), ensure your screws are appropriate for the thickness of that steel. You might need heavier gauge self-drilling screws or pre-drilling and self-tapping screws for thicker sections. Consult your frame engineer if uncertain.
Wet Area Plasterboard and Waterproofing
Bathroom, laundry, and toilet walls require specific attention.
- Moisture-Resistant Plasterboard (Green Board): Use this type of plasterboard in wet areas. It is water-resistant, not waterproof.
- Waterproofing Membrane: According to NCC 2022, Volume Two, Part 3.8.1 and AS 3740:2021, a continuous waterproofing membrane must be applied over the moisture-resistant plasterboard in critical wet zones (shower recesses, behind baths, etc., and up 150mm from the floor over the entire floor area). This work must be completed by a licensed waterproofer in some states (e.g., NSW, QLD, VIC) or certified as compliant by a building certifier.
- Floor-Wall Junction: Pay particular attention to the junction between the wet area floor and the wall plasterboard. The waterproofing membrane typically extends from the floor up the wall.
Cost and Timeline Expectations
Owner-builders need realistic expectations for both financial outlay and time commitment.
Cost Estimates (AUD, as of mid-2024)
Costs can fluctuate based on location, supplier, and specific product choices. These are indicative.
- Plasterboard Sheets:
- 10mm Standard: $12 - $18 per square metre (approx. $40 - $65 per 2400x1200mm sheet)
- 13mm Standard: $15 - $22 per square metre (approx. $50 - $80 per 2400x1200mm sheet)
- Moisture Resistant (10mm): $18 - $28 per square metre (approx. $65 - $100 per 2400x1200mm sheet)
- Fire-Rated / Acoustic (13mm+): $25 - $50+ per square metre (can be significantly more)
- Screws: $25 - $50 per box (1000 screws), depending on type and length. Budget for 10-15 screws per square metre of board.
- Jointing Compound:
- Base Coat: $30 - $50 per 20kg bag/bucket
- Top Coat: $35 - $60 per 20kg bag/bucket
- Allowance for average 3-4 bags/buckets each for a typical 3-bed home.
- Jointing Tape: $10 - $20 per roll.
- Corner Bead: $5 - $10 per 3m length.
- Stud Adhesive: $15 - $25 per 1L cartridge or $40 - $70 per 4L tub.
- Cornice: $5 - $15 per linear metre, depending on profile and material.
- Tools (Initial Investment): If starting from scratch, budget $500 - $1500 for essential tools (lifter, screw gun, T-square, levels, knives, etc.). Some items can be hired (e.g., plasterboard lifter).
- Waste Factor: Always factor in 10-15% extra for waste and cutting mistakes.
Total Material Cost Example (Typical 150sqm house): For a moderate-sized 3-bedroom house (approx. 400-500sqm of internal lining), expect material costs alone to range from $6,000 to $15,000+ AUD, depending on plasterboard types specified. This excludes labour if you were hiring a professional.
Owner-Builder Cost Saving: The biggest saving for owner-builders is labour. Professional plasterers charge between $35 - $60 per square metre (supply and install), or $25 - $40 per square metre (install only). For a 500sqm area, this is a saving of $12,500 - $30,000+ if you do it yourself.
Timeline Expectations
The time required is highly variable based on your experience, the complexity of the house, and your available working hours.
- Small (100-150 sqm lining area): 2-3 weeks (full-time effort)
- Medium (200-300 sqm lining area): 3-5 weeks (full-time effort)
- Large (350-500 sqm lining area): 5-8 weeks (full-time effort)
Breakdown of Stages:
- Preparation (Layout, cutting plans): 1-3 days
- Ceiling Sheets Installation: 3-7 days (can be slow without a lifter)
- Wall Sheets Installation: 5-10 days
- First Coat (Base Coat & Tape): 3-7 days (includes drying time)
- Second/Third Coat (Top Coat): 3-7 days (includes drying time)
- Sanding: 2-5 days (can be tedious)
- Cornice Installation: 2-4 days
Realistic Pace: As an owner-builder, expect to be slower than a professional crew initially. Factor in learning curves, potential for rectifying mistakes, and managing other aspects of the build. Don't rush the stopping and sanding phases; quality here dictates the final paint finish.
Common Mistakes to Avoid
Learning from others' errors can save significant time, money, and frustration.
- Incorrect Screw Type/Too Many Screws: Using timber screws on steel frames or over-driving/under-driving screws are common errors. Over-driving breaks the paper facing, creating weak points. Under-driving leaves proud screw heads. Too many screws simply wastes time and creates more 'bumps' to fill, while too few compromises fixing. Use the specific fine-thread drywall screws for steel frames with a setter bit, generally 150mm centres on edges, 300mm on field.
- Poor Joint Preparation: Not leaving a slight bevel on butt joints, failing to embed tape fully, or applying inconsistent coats leads to visible joints and cracks. Butt joints are the hardest to make invisible; take extra care on these.
- Insufficient Drying Time for Compound: Rushing between coats of jointing compound can lead to cracking, shrinking, and poor adhesion. ALWAYS allow recommended drying times, especially in cooler or humid conditions. This is a common shortcut that causes issues.
- Neglecting Fire-Rated/Moisture-Resistant Boards: Placing standard plasterboard in areas requiring specific performance (garage walls, wet areas) is a serious NCC violation and can lead to safety hazards or property damage. Always verify board types.
- Not Staggering Joints: Aligning all horizontal or vertical joints on adjacent sheets creates continuous weak lines prone to cracking. Always stagger joints (especially butt joints) to distribute stress.
- Incorrect Backing for Cut Edges: Cut edges of plasterboard (which lack the tapered edge) should always be supported by a stud, nogging, or timber blocking. If a cut edge ends up in the middle of a wall/ceiling without support, it's a weak point.
- Inadequate Safety Precautions: Falls from ladders, cuts from knives, and respiratory issues from dust are entirely preventable. Always prioritise PPE and safe work practices. Never work alone when handling large sheets.
- Plasterboard Directly on Floor: While common for timber, steel frames are generally very square. Plasterboard should sit just above the finished floor level (e.g., 10-15mm gap) to prevent moisture wicking and allow for flooring installation. This gap is covered by skirting boards. Use small offcuts of plasterboard or timber as temporary spacers during installation.
When to Seek Professional Help
While owner-building offers significant financial savings, there are critical junctures where engaging a licensed professional is prudent, or even mandatory.
- Structural Issues: If you identify significant deviations (bowing, twisting) in your steel frame that cannot be rectified easily, consult your steel frame supplier or a structural engineer immediately. Do not attempt to force plasterboard over structural defects.
- Complex Designs (Angles, Arches): If your design includes complex architectural features such as raked/cathedral ceilings, curved walls, or intricate archways, hiring a professional plasterer for these specific sections can ensure a superior finish and save you considerable frustration and material waste.
- Fire-Rated Systems: For specific Fire Resistance Level (FRL) requirements (e.g., party walls, fire-rated garages), consult with a fire engineer or professional plasterer experienced in these systems. The correct installation methodology (including specific screws, sealants, and multiple layers) is critical for compliance and safety, as outlined in NCC 2022, Volume One, Section C, Part C2.
- Waterproofing: As per AS 3740:2021 and state regulations, waterproofing of wet areas usually requires a licensed waterproofer. Even if you install the moisture-resistant plasterboard, the application of the membrane and certification is often a specialist trade. Check your local state building authority requirements.
- Large Scale & Time Constraints: If your project is extensive, or you have strict time constraints, sub-contracting the plasterboard installation (or at least the stopping/sanding) can be a wise investment to maintain project schedule and finish quality. Quality stopping is an art form that takes years to master.
- Building Certifier's Advice: Your independent building certifier/surveyor is your primary guide for regulatory compliance. If they advise you to seek professional assistance for a complex aspect of your build, heed their advice. They will be conducting mandatory inspections (e.g., pre-lining inspection) and ensuring overall compliance.
Remember: As an owner-builder, while you manage the project, you can still hire licensed trades for specific tasks. This is not a failure; it's smart project management that ensures quality and compliance where it's most critical.
Checklists and Resources
Pre-Installation Checklist
- Building permit and all relevant approvals obtained.
- Steel frame fully erected, plumb, and square (certified by engineer/frame supplier).
- All services (electrical, plumbing, HVAC) rough-ins complete and inspected (where required).
- Wall and ceiling insulation correctly installed and inspected (where required).
- Floors swept, work area clear and well-lit.
- All required plasterboard types delivered, stored flat, and acclimatised.
- All necessary tools (lifter, screw gun, knives, levels, tape, etc.) on site and in working order.
- PPE (glasses, gloves, dust mask, hearing protection) ready and visible.
- Reviewed plasterboard manufacturer's installation guide for specific products.
- Reviewed steel frame manufacturer's guidance on plasterboard fixing.
Installation Checklist
- Ceiling sheets installed first, perpendicular to battens/trusses.
- Appropriate self-drilling drywall screws used for steel frames.
- Screws spaced correctly (150-200mm perimeter, 300mm field) and recessed properly.
- Stud adhesive applied to steel studs/battens (if used) and compatible with steel.
- Wall sheets installed plumb, with correct gaps at floor (10-15mm) and ceiling.
- All joints staggered; no butt joints at window/door corners.
- All openings (lights, outlets, plumbing) accurately cut out.
- Moisture-resistant board used in all wet areas.
- Adequate ventilation during drying of jointing compound.
Post-Installation (Stopping & Finishing) Checklist
- All screw heads coated with base coat.
- All tapered joints taped and coated with base coat (first and second applications).
- All butt joints taped and built up carefully with base coat.
- External corners fitted with metal bead and coated.
- Internal corners taped and coated.
- All base coats fully dry before next layer.
- Top coats applied, smoothed, and fully dried.
- All jointed areas meticulously sanded smooth and flat.
- Cornices accurately cut, installed, and adhesive wiped clean.
- Final clean-up of dust and debris.
- Arrange for building certifier final inspection (pre-paint stage).
Key Resources
- National Construction Code (NCC): Free online access for Australian users via abcb.gov.au (registration required).
- Standards Australia: Purchase or subscribe to AS/NZS standards via standards.org.au.
- Your State Building Authority:
- NSW: Fair Trading (nsw.gov.au/fair-trading)
- QLD: QBCC (qbcc.qld.gov.au)
- VIC: VBA (vba.vic.gov.au)
- WA: Building & Energy (commerce.wa.gov.au/building-and-energy)
- SA: Office of the Technical Regulator (sa.gov.au/topics/building-and-property)
- TAS: CBOS (cbos.tas.gov.au)
- Plasterboard Manufacturers: CSR Gyprock (gyprock.com.au), Boral Plasterboard (boral.com.au) – excellent technical libraries and installation guides.
- Steel Frame Manufacturers: BlueScope Steel / TRUECORE® (truecore.com.au) – often provide design and installation manuals specific to their framing systems.
- Work Health and Safety (WHS): Safe Work Australia (safeworkaustralia.gov.au) for general WHS guidance.
Key Takeaways
Installing plasterboard on a steel frame for your kit home is a highly achievable task for an owner-builder with careful planning and execution. The precision of steel frames, particularly those utilizing TRUECORE® steel, significantly simplifies the process compared to working with less predictable timber. However, success hinges on meticulous attention to detail, adherence to Australian regulations (NCC and AS/NZS), and the use of correct materials specific to steel construction.
Always prioritise safety, use appropriate self-drilling screws, ensure adequate joint preparation and drying times, and never compromise on the required type of plasterboard for specific areas (e.g., wet areas, fire-rated zones). While the journey is challenging, the reward of stepping back and admiring your perfectly finished, self-installed interior linings is immense. Don't hesitate to consult with professionals for complex sections or mandatory inspections, leveraging their expertise to ensure your home is not only beautiful but also safe, compliant, and durable for decades to come.
By following this comprehensive guide, you are well on your way to achieving a professional-grade finish for the internal linings of your steel frame kit home, adding significant value and satisfaction to your owner-builder project. Good luck, and enjoy the process of bringing your vision to life!