Project Management intermediate

Mastering Trade & Delivery Scheduling for Your Steel Frame Kit Home

IK

IKH Team

February 27, 2026

24 min read
Back to Guides

Mastering Trade & Delivery Scheduling for Your Steel Frame Kit Home in Australia

Welcome, aspiring owner-builder! Embarking on the journey of constructing your own steel frame kit home in Australia is a monumental undertaking, promising immense satisfaction alongside significant challenges. One of the most critical, yet often underestimated, aspects of successful project management is the meticulous scheduling of trades and deliveries. Without a well-thought-out plan, your build can quickly descend into chaos, leading to delays, cost blowouts, frustrated tradespeople, and potential safety hazards. This comprehensive guide, tailored specifically for Australian owner-builders of steel frame kit homes, will equip you with the knowledge and actionable strategies to navigate this complex terrain effectively.

Why Effective Scheduling Matters for Owner-Builders

As an owner-builder, you are essentially acting as the project manager, a role traditionally held by a professional builder with years of experience. This means you bear the responsibility for coordinating all facets of the construction process. For steel frame kit homes, this coordination becomes even more nuanced. You're dealing with precise, pre-fabricated components (often from BlueScope Steel or made with TRUECORE® steel) that require specific lifting equipment and often need to be erected sequentially. Unlike traditional timber framing where minor on-site adjustments are more feasible, steel frames demand accuracy and a firm schedule for their delivery and erection.

Poor scheduling can lead to:

  • Cost Overruns: Idle tradespeople still charge for their time, materials sitting on site for too long risk damage or theft, and expedited deliveries incur extra fees.
  • Project Delays: One delayed trade can have a cascading effect, pushing back subsequent stages and potentially missing critical weather windows or inspection deadlines.
  • Quality Compromises: Rushed work due to tight schedules, or trades working out of sequence, can lead to substandard finishes or structural issues.
  • Safety Hazards: An unorganised site with materials haphazardly stored or trades working over each other increases the risk of accidents.
  • Stress and Frustration: For you, your family, and the tradespeople involved. Building a home is stressful enough without avoidable scheduling headaches.
  • Compliance Breaches: Missed inspection windows or not having the site ready for critical sign-offs can lead to non-compliance with regulatory requirements.

This guide will walk you through the entire process, from understanding the regulatory landscape to practical tips for managing your site, ensuring your steel frame kit home build progresses smoothly, safely, and within budget.

Understanding the Basics: Your Toolkit for Project Management

Before diving into the specifics of scheduling, it's crucial to grasp some fundamental project management principles and tools that will form the backbone of your strategy.

The Critical Path Method (CPM)

The Critical Path Method (CPM) is a project management technique that identifies the sequence of project activities that determines the shortest possible duration to complete the project. Activities on the critical path cannot be delayed without delaying the entire project.

For your steel frame kit home, activities like slab pouring, frame erection, and roof installation are often on the critical path. Understanding this allows you to prioritise resources and closely monitor these key milestones.

Gantt Charts

A Gantt chart is a visual representation of a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project. Using a Gantt chart will help you:

  • Visualise the entire project timeline.
  • Identify dependencies between tasks.
  • Track progress against your plan.
  • Communicate the schedule clearly to trades and suppliers.

Simple Gantt charts can be created using spreadsheets (e.g., Excel, Google Sheets), or dedicated project management software (e.g., Asana, Trello, Microsoft Project for more complex needs).

Key Milestones and Dependencies

Break your project down into manageable milestones. For a steel frame kit home, these typically include:

  1. Site Preparation: Clearing, levelling, earthworks.
  2. Slab/Foundation: Formwork, rebar, concrete pour (critical dependency for frame).
  3. Frame Erection: Assembly of steel walls and roof trusses (kit delivery is critical here).
  4. Roofing: Installation of roof sheeting and gutters.
  5. External Cladding: Installation of exterior walls, windows, and doors.
  6. Rough-in Services: Electrical, plumbing, HVAC – prior to internal lining.
  7. Insulation: Wall and ceiling insulation.
  8. Internal Lining: Plasterboard/gyprock.
  9. Finishing Trades: Painting, flooring, joinery, fitting out.
  10. Final Inspections and Handover.

Each of these has dependencies. For example, roof installation cannot begin until the frame is erected. Electrical rough-in cannot commence until the frame is complete and often requires roof sarking or even roof sheeting to be in place for safety and weather protection. Material deliveries must always precede the work needing them.

Buffer Time (Contingency)

Always build in buffer time. Things will go wrong: weather delays, trade availability issues, material shortages, or inspection delays. A general rule of thumb is to add at least 10-15% contingency time to your overall schedule. This buffer allows you to absorb minor setbacks without pushing out your entire project.

Australian Regulatory Framework for Scheduling

Navigating the Australian regulatory landscape is paramount. Your schedule must accommodate statutory inspections, WHS requirements, and specific state regulations.

National Construction Code (NCC)

The NCC, comprising the Building Code of Australia (BCA) and the Plumbing Code of Australia (PCA), sets minimum standards for health, safety, amenity, accessibility, and sustainability for buildings. Your schedule must allow for compliance inspections at various stages.

Key NCC considerations:

  • NCC 2022, Volume Two, Part H1 – Structure: This part outlines the requirements for structural components, including steel framing. Your building surveyor will inspect the frame before cladding to ensure compliance with engineering designs and AS/NZS standards.
  • NCC 2022, Volume Two, Part 3.5.1 – Slab-on-ground construction: Requires inspections before concrete pour, ensuring correct formwork, membrane, and reinforcement placement.
  • NCC 2022, Volume Two, Part 3.10 – Construction in bushfire prone areas: If applicable, specific materials and construction methods will need to be inspected at various stages to confirm compliance with AS 3959.

Your building permit will specify the mandatory hold points for inspection by your appointed building surveyor. These are non-negotiable and must be scheduled. Work cannot proceed beyond a hold point until signed off. Common hold points include:

  1. Footings/Slab Reinforcement Inspection: Before concrete pour.
  2. Structural Frame Inspection: Before cladding/lining (critical for steel frames).
  3. Plumbing Rough-in Inspection: Before covering pipes.
  4. Stormwater Inspection: Before backfilling.
  5. Final Inspection: Before occupation permit/certificate of final inspection.

Australian Standards (AS/NZS) & Safety

AS/NZS 4600:2018 - Cold-formed steel structures: This is the primary standard governing the design and construction of steel framing. Your kit home will be engineered to this standard, and its erection must conform. Trades working on your frame, particularly those involved in structural connections, must be familiar with its requirements.

AS/NZS 1562.1:2018 - Design and installation of sheet roof and wall cladding - Part 1: Metal: Pertains to the installation of metal roofing, which is common for steel frame homes. Ensures correct fastening, flashing, and weatherproofing.

Work Health and Safety (WHS) Act 2011 (Cth) and associated state legislation: Owner-builders have significant WHS obligations. Your site must be safe for all persons, including trades, visitors, and yourself. Scheduling plays a direct role in WHS by preventing overcrowding, ensuring clear access, and allowing for proper material handling and storage.

Key WHS considerations for scheduling:

  • Site Induction: All trades must receive a site induction. Schedule time for this.
  • Safe Work Method Statements (SWMS): For high-risk activities (e.g., working at heights, operating machinery), SWMS are required from trades. Factor in time for review and discussion.
  • Clear Work Areas: Don't schedule multiple trades in the same small area concurrently. Consider spatial demands for each trade.
  • Access and Egress: Ensure safe pathways, scaffolding, and ladders are in place when needed.
  • Material Handling: Schedule deliveries to avoid double handling. Large steel sections require forklifts or cranes, which need clear access and setup time.

State-Specific Variations

While the NCC provides a national framework, each state and territory has specific legislative instruments and regulatory bodies that govern building and WHS matters.

  • New South Wales (NSW): Regulated by NSW Fair Trading (for owner-builders) and NSW Planning for building approvals. Specific requirements for owner-builder permits (if work value exceeds ~$10,000 AUD). WHS by SafeWork NSW. Inspections by a Principal Certifying Authority (PCA).
  • Queensland (QLD): Building regulated by the Queensland Building and Construction Commission (QBCC). Specific owner-builder permit rules (for work exceeding ~$11,000 AUD). WHS by Workplace Health and Safety Queensland. Inspections by a private building certifier.
  • Victoria (VIC): Building regulated by the Victorian Building Authority (VBA). Owner-builder certificate of consent required (for work exceeding ~$19,000 AUD). WHS by WorkSafe Victoria. Inspections by a Private Building Surveyor.
  • Western Australia (WA): Building regulated by the Department of Mines, Industry Regulation and Safety (DMIRS). Owner-builder permit required for work exceeding ~$20,000 AUD. WHS by WorkSafe WA. Inspections by a private building surveyor or local government.
  • South Australia (SA): Building regulated by Consumer and Business Services (CBS). Owner-builder exemptions apply, but significant responsibilities. WHS by SafeWork SA. Inspections by a private building certifier or local council.
  • Tasmania (TAS): Building regulated by the Department of Justice, Consumer, Building and Occupational Services (CBOS). Owner-builder registrations and specific forms required. WHS by WorkSafe Tasmania. Inspections by a building surveyor.

Action Point: Before commencing any scheduling, contact your relevant state building authority to confirm current owner-builder requirements, permit thresholds, and specific inspection processes in your area. This will directly impact your schedule and budget.

Step-by-Step Process for Effective Scheduling

This methodical approach will guide you through creating and managing your project schedule.

Step 1: Develop Your Scope of Work and Detailed Bill of Materials

Before you can schedule, you must know what needs to be done and what materials are required.

a. Review Kit Home Plans and Inclusions: Go through your kit home plans and specifications with a fine-tooth comb. Understand every component, connection, and sequence. Your kit home supplier (e.g., a supplier of TRUECORE® steel frames) will provide detailed erection manuals. These are your bible.

b. Break Down Tasks (Work Breakdown Structure - WBS): List every single task, no matter how small. Examples: 'Trench for services,' 'Install waterproofing membrane,' 'Caulk windows.'

c. Create a Comprehensive Bill of Materials (BOM): While your kit home supplier provides the frame, you'll need to source many other materials: concrete, rebar, plumbing fittings, electrical wiring, insulation, plasterboard, tiles, paint, etc. List quantities, specifications, and preferred suppliers for each.

Step 2: Establish Task Durations and Dependencies

a. Estimate Task Durations: For each task identified in Step 1, estimate how long it will take. Be realistic, and err on the side of caution. Consult experienced trades or your kit home supplier for typical durations.
* Example: Slab preparation (formwork, rebar, plumbing rough-in): 3-5 days. Concrete pour: 0.5-1 day. Frame erection (standard single-storey kit): 5-10 days. Roofing (metal): 3-7 days.

b. Identify Dependencies: For each task, determine which other tasks must be completed before it can start. For instance, you can't install internal wall insulation until electrical and plumbing rough-ins are complete and inspected.

c. Sequence Your Tasks: Arrange tasks in a logical order based on dependencies. This forms the backbone of your Gantt chart.

Step 3: Source and Engage Trades and Suppliers

a. Obtain Multiple Quotes: Always get at least three quotes for each trade and major material supply. Don't just go for the cheapest; critically assess experience, references, insurance, and availability.

b. Verify Licences and Insurance: This is non-negotiable. Always check current licences (e.g., through QBCC licence search, NSW Fair Trading public register) and request a Certificate of Currency for Public Liability and Workers' Compensation insurance. Ensure coverage for the scope of work.

c. Discuss Availability and Scheduling Expectations: When engaging trades, clearly communicate your proposed timeline. Ask about their typical lead times and confirm their availability for your specific construction phases. Be prepared to be flexible, especially for high-demand trades.

d. Formalise Agreements (Contracts): For significant work, use a written contract. This doesn't have to be overly complex but should cover:
* Scope of work and specifications.
* Agreed price and payment schedule.
* Start and finish dates.
* Responsibilities for materials, waste removal, WHS.
* Dispute resolution process.

Owner-builder warning: In some states, such as NSW and QLD, specific forms of contract are required for certain types of work, even when you're the owner-builder engaging a sub-contractor.

Step 4: Create Your Master Schedule (Gantt Chart)

a. Choose Your Tool: Start with a simple spreadsheet for a basic Gantt chart. Columns might include: Task Name, Start Date, End Date, Duration, Predecessors, Assigned Trade, Status. Use conditional formatting to visually represent timelines.

b. Input Data: Transfer all your tasks, durations, and dependencies into your chosen scheduling tool.

c. Allocate Resources (Trades): Assign specific trades to each task. This helps you balance workloads and identify potential bottlenecks where one trade is needed for multiple concurrent tasks.

d. Integrate Deliveries: Crucially, integrate all major material deliveries. When your steel frame kit (BlueScope Steel/TRUECORE®) is scheduled for delivery, ensure you have:
* Clear site access for large trucks.
* Space for safe unloading and storage.
* Lifting equipment (crane/forklift) booked and available if needed.
* Your frame erectors ready to commence immediately after delivery to minimise exposure to elements and reduce theft risk.

*Example of a delivery integration:* If your frame erection starts on Monday, the steel frame kit *must* be delivered on the preceding Friday or Monday morning. Crane *must* be scheduled for the first day of erection.

e. Incorporate Inspections: Mark all mandatory building surveyor inspections (hold points) clearly on your schedule. Build in buffer time before these inspections in case minor rectifications are required.

f. Add Buffer Time: Systematically add contingency time. For example, add a day or two between major trade handovers.

Step 5: Implement and Monitor Your Schedule

a. Communicate the Schedule: Share your master schedule with all engaged trades and key suppliers. A clear, visual schedule reduces misunderstandings.

b. Daily/Weekly Check-ins: Routinely check in with trades. Confirm they are on schedule, identify any potential delays early, and address issues proactively. A brief site meeting each morning can be invaluable.

c. Track Progress: Regularly update your Gantt chart with actual start and finish dates. This allows you to see if you're ahead or behind schedule and adjust accordingly.

d. Problem Solving: Be prepared for things to go wrong. When delays occur, identify the cause, assess its impact on the critical path, and adjust your schedule. Communicate changes immediately to affected parties.

Step 6: Adapt and Re-evaluate

Your schedule is a living document. It will evolve. Be flexible, but maintain control. Regular reviews (e.g., weekly) of what's coming up in the next 2-4 weeks are essential.

Practical Considerations for Steel Frame Kit Homes

Steel frame kit homes present unique scheduling challenges and advantages.

Precise Delivery & Unloading

  • Kit Delivery: The entire steel frame kit, often made from TRUECORE® steel, will arrive largely pre-cut and pre-punched. This is a significant, often heavy, delivery. Confirm the exact delivery date and time with your supplier well in advance. Consider arranging for a dedicated delivery slot.
  • Site Accessibility: Ensure your site is accessible for large trucks (often semi-trailers). Clear any obstructions and prepare a firm, level area for unloading.
  • Unloading Equipment: Determine if a forklift or crane is required for unloading. Your kit supplier should advise this. If so, book these well in advance – crane hiring can be competitive and costly (AUD $200-$400/hour, minimum hours often apply).
  • Storage: Designate a secure, dry area to store your steel components. While steel is resistant to immediate water damage, organised storage prevents loss, speeds up erection, and mitigates rust if left exposed for extended periods. Protect smaller components and connection kits from theft.

Frame Erection Specialists

  • Dedicated Team: While some owner-builders might tackle steel frame erection with sufficient experience and equipment, many opt for specialist steel frame erectors. These teams are highly efficient and familiar with the specific fastening and assembly techniques for products like those from BlueScope Steel.
  • Coordination with Crane/Forklift: If using lifting equipment, their schedule must align perfectly with your frame erectors. A crane sitting idle waiting for a team costs you money.
  • Weather Sensitivity: While steel frames are less susceptible to weather damage during erection than timber, strong winds can make lifting large sections unsafe. Have a contingency plan for wind delays.

Early Rough-Ins and Follow-On Trades

  • Plumbing & Electrical: Because steel frames are pre-punched, the locations for services are fixed. Your plumbers and electricians need to understand this. You might schedule a 'pre-rough-in' site visit for them before the frame is erected, or at the very least, have them review the frame erection plans. They must be ready to move quickly after the frame inspection.
  • Roofing: As soon as the frame is certified, roofers should be onsite. Getting the roof on provides weather protection for the interior, allowing other trades to work more efficiently and protecting your investment.
  • Windows & Doors: Once the frame is up, ordering final window and door sizes can be done (if not already custom ordered off plan). Schedule their installation shortly after the roof is on and before external cladding, as they define critical openings.

Material Ordering Lead Times

  • Custom Items: Custom windows, specialized doors, or custom joinery can have lead times of 4-12 weeks. Order these early in your project.
  • Standard Items: Plasterboard, insulation, timber, cement boards generally have shorter lead times (1-2 weeks), but always confirm stock before scheduling a trade.
  • Bulk Deliveries vs. Just-in-Time: For heavy materials like concrete batches, aim for just-in-time delivery to minimise site clutter and potential damage. For lighter, less perishable items like plasterboard, an earlier delivery might be acceptable if secure storage is available, allowing trades to start immediately.

Cost and Timeline Expectations (AUD)

These are rough estimates and can vary significantly based on location, complexity, and contractor availability.

Typical Build Phases & Durations for a Single-Storey Steel Frame Kit Home (Approx. 150-200m²)

Phase Duration (Weeks) Key Trades/Deliveries Potential Cost Impact of Delays
Planning & Permits 12-24 Building surveyor, local council, engineer None (pre-build)
Site Prep & Footings/Slab 2-4 Earthmover, plumber, concreter, reo supplier, concrete supplier Machine hire, concreter idle time (AUD $1000+/day)
Steel Frame Erection 1-2 Steel framers, crane/forklift hire, kit delivery Crane hire, framers idle, weather exposure (AUD $1500+/day)
Roofing 1-2 Roofers, roof sheeting delivery Weather damage to frame/slab (AUD $5000+), roofer delays
External Enclosure 2-4 Window/door installers, general builders, cladding materials Delay for subsequent trades (AUD $800+/day)
Rough-in (Plumbing/Elec/HVAC) 2-3 Plumbers, electricians, HVAC installers Knock-on delays for internal sheeting (AUD $800+/day)
Insulation & Plaster Drywall 2-3 Insulators, plasterers, plasterboard delivery Prolongs internal fit-out
Internal Fit-out & Finishes 4-8 Painters, tilers, cabinet makers, flooring, general Prolonged ownership costs, late completion
Final Inspections & Clean 1-2 General cleaner, building surveyor Occupation delays
Total Estimated Time ~18-30 Weeks (4.5-7.5 months)

Hourly/Daily Rates for Key Trades (Approx. AUD, incl. GST & Labour only)

Trade Hourly Rate Day Rate (8hrs) Note
General Labourer $40 - $60 $320 - $480 For general site clean-up, assistance
Concreter $60 - $90 $480 - $720 Often quote per m² for slab work
Steel Frame Erector $80 - $120 $640 - $960 Highly specialised
Roofer (metal) $70 - $100 $560 - $800 Often quote per m² for installation
Plumber $80 - $120 $640 - $960 For licensed work
Electrician $80 - $120 $640 - $960 For licensed work
Plasterer $70 - $100 $560 - $800 Often quote per m² for sheeting and setting
Carpenter (finishing) $70 - $100 $560 - $800 For doors, architraves, skirting
Painter $60 - $90 $480 - $720 Often quote per m² for surface area
Building Surveyor $1500 - $4000 (total project fees) N/A Essential compliance, multiple visits
Crane Hire $200 - $400 $1600 - $3200+ (often min 4hrs) Plus mobilisation/demobilisation fees

Important: These figures are indicative. Obtain direct quotes for your specific project. Delays mean you're paying for idle trades or incurring additional mobilisation/demobilisation fees for equipment.

Common Mistakes to Avoid in Scheduling

Owner-builders, particularly those new to steel frame construction, often fall into predictable pitfalls.

  1. Underestimating Task Durations: Always add a buffer. New skills take longer to learn. Unforeseen issues take time to resolve. Assume things will take longer than you initially think.
  2. Neglecting Dependencies: Thinking roofers can start before the frame is inspected, or electricians before plumbers, is a recipe for disaster. Strict adherence to the critical path and dependencies is crucial.
  3. Poor Communication with Trades: Assuming trades will intuitively know your schedule is a mistake. Regular, clear communication, shared schedules, and proactive check-ins are vital. Confirm work dates a week in advance and then again 1-2 days prior.
  4. Not Factorising Deliveries: Forgetting to order materials until the trade is due can cause days or weeks of delay. Not having adequate storage space for a large steel frame kit delivery leads to problems.
  5. Ignoring WHS Requirements: Scheduling trades to work simultaneously in confined spaces, or failing to provide safe access (e.g., scaffolding for roofers), is not only dangerous but can lead to fines, stop-work orders, and legal liabilities under state WHS acts.
  6. Failing to Budget for Delays: Delays cost money. Have a financial contingency plan (15-20% of total project cost) to cover unexpected expenses from schedule disruptions.
  7. Overlapping Trades in the Same Space: While some overlap is inevitable (e.g., plumber and electrician during rough-in, if coordinated), scheduling multiple demanding trades in the same confined internal space leads to inefficiency, frustration, and potential safety issues. Plan for clear work zones.
  8. Not Reviewing Kit Erection Manuals Thoroughly: For a steel frame kit home using say, TRUECORE® steel, the erection manual is highly specific. Failure to understand critical details (e.g., bolt tightening sequences, bracing requirements) can lead to delays during erection or even structural non-compliance, requiring rework.

When to Seek Professional Help

While this guide empowers you, there are specific instances where engaging professionals is not just advisable, but often mandatory or financially prudent.

  • Complex Engineering Challenges: If your site has unusual soil conditions, is on a steep slope, or your design features complex cantilevered sections, you'll need a structural engineer (fully licenced) beyond the kit home's standard designs. Their input will often dictate parts of your schedule.
  • Mandatory Building Surveyor/Certifier: As discussed, a building surveyor/certifier is legally required in all states to approve your plans and conduct mandatory inspections. They are a critical part of your schedule and must be engaged early.
  • High-Risk Work: For activities explicitly deemed 'high-risk construction work' under WHS regulations (e.g., working at heights over 2m, demolition of load-bearing structures, work near energised electrical installations), consider engaging licensed and experienced contractors who can provide Safe Work Method Statements (SWMS) and ensure compliance. This includes safe erection of your steel frame if you're not experienced.
  • Specialised Trades: Electrical, plumbing, gas fitting, and often waterproofing are trades that must be carried out by licensed professionals. Incorporate their specific scheduling needs and inspection requirements.
  • Financial Management: If you struggle with budgeting or tracking expenses, a financial advisor or bookkeeper familiar with construction projects can help manage cash flow and ensure funds are available when needed for trades and materials.
  • Building Consultants/Project Managers: For owner-builders feeling overwhelmed, engaging a building consultant or a part-time project manager can provide invaluable guidance, especially in navigating regulatory hurdles, reviewing quotes, and, critically, setting up and monitoring a robust schedule.

Pro Tip: Don't hesitate to consult your kit home supplier (e.g., those using BlueScope Steel or TRUECORE® products) for advice on typical erection times, recommended lifting equipment, and any specific requirements for their system. They often have networks of experienced erectors they can recommend.

Checklists and Resources

Use these tools to stay organised and on track.

Pre-Construction Scheduling Checklist

  • Finalised and approved building plans.
  • Building permit obtained.
  • Owner-builder permit/certification obtained (if required by state).
  • Building surveyor/certifier appointed and aware of project timeline.
  • Detailed Work Breakdown Structure (WBS) created.
  • Comprehensive Bill of Materials (BOM) for non-kit items.
  • Lead times confirmed for all major materials (especially custom items).
  • At least 3 quotes obtained for each major trade.
  • Licences and insurance verified for all selected trades.
  • Written contracts in place with key trades.
  • Master schedule (Gantt chart) created, incorporating all tasks, dependencies, deliveries, and inspections.
  • WHS plan developed, including site induction, SWMS requirements.
  • Financial contingency (15-20%) allocated.
  • Site layout plan created (storage, access, safety zones).

During Construction Scheduling Checklist

  • Daily/weekly schedule review with trades where applicable.
  • Site inductions conducted for all new personnel.
  • Progress tracked against the schedule.
  • Proactive communication regarding upcoming tasks and potential issues.
  • Deliveries confirmed 1-2 days prior.
  • Site kept clear, safe, and organised.
  • Mandatory inspections booked and passed on time.
  • Payments to trades reconciled against work completed.
  • Records of all communications and decisions maintained.

Useful Resources

Key Takeaways

Successful scheduling for your steel frame kit home is the cornerstone of a smooth, cost-effective, and safe build. Remember:

  • Plan, Plan, Plan: A detailed schedule (Gantt chart) is your roadmap. Don't skimp on pre-construction planning.
  • Understand Dependencies: Follow the critical path. One delayed task can ripple through the entire project.
  • Communicate Constantly: Keep all trades and suppliers informed of your schedule and any changes.
  • Budget for Contingency: Both time and money. Unexpected events are a certainty, not a possibility.
  • Prioritise Safety: Your schedule must always accommodate WHS requirements, ensuring clear work zones and safe practices.
  • Leverage Your Kit Supplier: They are a valuable resource for specific steel frame erection advice and timelines.
  • Be Adaptable: Your schedule is a living document. Be prepared to adjust, but always maintain control and clear communication.

By diligently applying these principles, you will transform the complex task of owner-building into a manageable and ultimately rewarding experience, culminating in the home of your dreams, built on a solid foundation of meticulous planning and execution.